The project includes the performance of modernisation works at 151 km of the line in the areas of the Local Control Centers (LCC) in Nasielsk, Działdowo and Tczew and the first stage of modernisation of the Gdynia Główna Osobowa station and also the purchase of lands for the implementation of 3rd stage of the modernisation.
The modernisation works will be performed based on 16 contracts:
1. Ten contracts for construction works:
- Nasielsk LCC area: modernisation of Legionowo, Nowy Dwór Mazowiecki, Modlin stations;
- Nasielsk LCC area: modernisation of routes: Legionowo – Nowy Dwór Mazowiecki, NowyDwór Mazowiecki – Nasielsk, Nasielsk – Świerszcze;
- Nasielsk LCC area: Warsaw East – Legionowo section, Nasielsk station;
- Nasielsk LCC area: construction of 17 two-level crossings;
- re-building of Gdynia station, stage 1;
- Tczew LCC area: modernisation of Tczew and Pszczółki stations and modernisation of Szymankowo – Tczew, Tczew – Pszczółki, Pszczółki – Pruszcz Gdański routes;
- Tczew LCC area: construction of 2 two-level crossings;
- Działdowo LCC area: modernisation of Iłowo, Działdowo, Gralewo, Rybno Pomorskie, Montowo stations;
- modernisation of Mława- Iłowo, Iłowo – Działdowo, Działdowo – Gralewo, Gralewo – Rybno Pomorskie, Rybno Pomorskie – Montowo routes;
- Działdowo LCC area: construction of two-level crossings;
2. Four contracts for Contract Engineer supervision over the construction works performance:
- Nasielsk LCC area;
- Działdowo LCC area;
- Tczew LCC area;
- Gdynia Główna station, stage I;
3. One contract for project management by a Project Manager;
4. One contract for information and promotion activities.
Thus far, the following contracts have been concluded:
1. Modernisation of the Gdynia Główna Osobowa station, stage 1
- contract number: 2005/PL/16/C/PT/001-01
- concluded on: June 12th , 2007
- performance period: 30 months upon the commencement of works
- contractor: Consortium: Budimex Dromex S.A./Ferrovial Agroman S.A.,
- contract value: EUR 38 092 795;
2. Construction works in the Nasielks LCC area, on Warsaw – Legionowo section and Nasielsk station
- contract number: 2005/PL/16/C/PT/001-08,
- concluded on: June 29th , 2007
- performance period: 20 months upon the commencement of works,
- contractor: Consortium: „PKP Energetyka” Sp. z o.o./Przedsiębiorstwo Napraw Infrastruktury Sp. z o.o.
- contract value: EUR 151 467 479.
3. Supervision over the modernisation of Gdynia Główna Osobowa station, stage 1
- contract number: 2005/PL/16/C/PT/001-02,
- concluded on: November 13th , 2007
- performance period: 42 months upon the signing date
- contractor: Consortium: TPF PLANEGE – Consultores de Engenharia e Gestao S.A. oraz E&L Architects Sp. z. o. o.
- contract value: EUR 1 040 022.42
4. Management of the project no. FS 2005/PL/16/C/PT/001 “Modernisation of E 65 railway line, Warsaw – Gdynia section, stage 2”
- contract number: 2005/PL/16/C/PT/001 – 06
- concluded on: November 30th , 2007
- scheduled completion: June 30th , 2011
- contractor: Consortium: WYG International Sp. z. o. o., Bud – Inwent Sp. z. o. o., WYG Consulting Limited
- contract value: EUR 879 000.00
5. Supervision over the modernisation of the Warsaw East – Nasielsk section of the E 65 railway line, Nasielsk LCC area
- contract number: 2005/PL/16/C/PT/001-10
- concluded on: November 30th , 2007
- performance period: 48 months upon the signing date of the contract
- contractor: Consortium: Arcadis Profil Sp. z. o. o., Biuro Realizacji Inwestycji Koltech Inwestor Sp. z. o. o.
- contract value: EUR 4 439 000.00
6. Construction works in the Nasielsk LCC area: LOT A – a comprehensive modernisation of the Legionowo, Nowy Dwór Mazowiecki, Modlin stations,
- contract number: FS 2005/PL/16/C/PT/001-03 LOT A
- concluded on: June 17th , 2008
- performance period: 24 months upon the signing date
- contractor: Trakcja Polska S.A. Consortium consisting of: Przedsiębiorstwo Robót Kolejowych i Inżynieryjnych S.A., Przedsiębiorstwo Robót Komunikacyjnych – 7 S.A., Przedsiębiorstwo Robót Komunikacyjnych w Krakowie, Bombardier Transportation (ZWUS) Polska Sp. z.o.o.
- contract value: EUR 101 117 014. 036
7. Supervision over the modernisation of the section from 287,700 km to 315,700 km of the E 65 railway line (Tczew LCC area)
- contract number: FS 2005/PL/16/C/PT/001-11
- concluded on: August 26th , 2008
- performance period: 36 months upon the commencement of works
- contractor: Consortium of MGGP S.A. and Agua Estructuras S.A.
- contract value: EUR 1 852 000.00
8. Modernisation of the E65 Warsaw – Gdynia railway line on section from 287,700 km (on Szymankowo – Lisewo route) to 315,700 km (Pszczółki – Pruszcz Gdański route) included in the area of the Local Control Center in Tczew
- contract number: FS 2005/PL/16/C/PT/001-4a
- concluded on: January 9th , 2009
- completion deadline: December 15th 2010
- contractor: consortium consisting of , ‘PKP Energetyka’ sp. z o.o. . – Proxy (Leader) of the Consortium, Przedsiębiorstwo Napraw Infrastruktury spółka z o.o. . – Partner, FEROCO S.A. – Partner, Bombardier Transportation (ZWUS) Polska spółka z o.o.– Partner, Pomorskie Przedsiębiorstwo Mechaniczno – Torowe spółka z o.o - Partner, Torpol spółka z o.o. - Partner
- contract value: EUR 305 271 942.15
-
The project value according to the decision of the European Commision of 2005: EUR 475 522 000
(actual value: EUR 1 046 400 000).
-
Sources of financing: Cohesion Fund (84%), State Budget (16%).
-
Performance period: August 26th , 2004 – December 31st , 2010.